GAIL India commissions Dabhol-Bengaluru gas pipeline

GAIL India on 18 February 2013 commissioned a pipeline carrying gas from Dabhol LNG terminal at Ratnagiri in Maharashtra to Bengaluru.  The Rs 4,500 crore Dabhol-Bengaluru pipeline can carry 16 million standard cu mtrs of gas per day and the 73 km laid in the city will help initiate CNG supplies to automobiles as well as piped cooking gas to households. The 1,000-km gas pipeline will help industries in Belgaum, Dharwad, Gadag, Bellary, Davanagere, Chitradurga, Tumkur, Ramanagaram and Bangalore that have been burdened by costly and polluting liquid fuels such as naphtha and diesel. 

GAIL India Ltd : GAIL Bhawan, 16, Bhikaiji Cama Place, New Delhi 110066.  www.gailonline.com

Heidelberg Cement raises clinker, cement capacity in MP

Heidelberg Cement India has expanded its clinker manufacturing capacity and cement grinding capacity in Madhya Pradesh. The company has raised the clinker manufacturing capacity from 1.2 million tpa to 3.1 million tpa and cement grinding capacity from one million tpa to two million tpa at its Narsingarh and Imlai units in Damoh district respectively. With the increased capacity going on stream, the company has completed its over Rs 1,500 crore expansion project to raise its all India production capacity from from 3.1 million tpa to six million tpa.

Heidelberg Cement India Ltd : Infinity Tower C, DLF Cyber City - Phase II, Gurgaon 122002

Monday, January 4, 2016

 Ford India (P) Ltd's Sanand plant near Ahmedabad, built with an investment of Rs 6,000 crores




 Radisson Goa hotel at Candolim, North Goa opened its doors in March 2015



 Sasan Power Ltd's Ultra Mega Thermal Plant at Sasan, Madhya Pradesh. 


Projects Commissioned during March 2015


Hospitality
Carlson-Rezidor Group
Chimes, Block A, First Floor,
Plot No 61, Sector 44
Gurgaon 122001
(Hq : Minnetoka, USA)

Radisson Goa
Carlson Rezidor Hotels Group
Candolim, Goa
(80 room luxury hotel in North Goa beach district opened in March 2015)

Engineering -automobile
Ford Motors India (P) Ltd
Ford Motors Complex
Singa Perumal Kovil Post
National Highway 45
Chengalpattu, ^ Chennai.  

Ford Motors India (P) Ltd
P.O. Kotpura, Sanand,
Gujarat
(Rs 6,000 crore 2.4 lakh capacity car and engine manufacturing plant spread over 456 acre land at Sanand near Ahmedabad inaugurated on March 26, 2015)

Energy
N.T.P.C Ltd
NTPC House,
SCOPE Complex,
Lodhi Road, New Delhi 11003
NTPC Ltd
Barh Thermal Power Plant
Barh, District Patna, Bihar
(660 MW Unit II of 1980 MW thermal power plant at Barh, 50 km east of Patna, operationalized in March 2015)

Chemicals & Pharma
Omkar Specialty Chemicals Ltd
B-34,  MIDC Badlapur (East)
District Thane, MMR

Omkar Specialty Chemicals Ltd
B- 15/16, Lote Parshuram
MIDC Chiplun, District Ratnagiri
Maharashtra
(Rs 100 crore specialty chemicals and pharma intermediaries plant commissioned in March 2015)

Energy
OPG Power Ventures Plc
IOMA House, Hope Street
Isle of Man

OPG Power Gujarat (P) Ltd
Bhadreshwar, District Kutch, Gujarat
(Rs 1,850 crore 300 MW coal fired power station inaugurated in Engineering -automobile March 2015)

Energy
Reliance Power Ltd
H Block, Dhirubhai Ambani
Knowledge City
Thane-Belapur Road
Kopar Khairane, Navi Mumbai 400710
Sasan Power Ltd
(subsidiary of Reliance Power Ltd)
Sasan, District Singrauli, MP
(660 Mw Unit 6 of 3,960 MW Ultra Mega Power Plant commissioned on March 31, 2015. Sasan UMPP is the largest coal-cum-power plant in the world)

Cement
Shree Cement Ltd
Bangur Group
21, Strand Road,
Kolkata 700001
Shree Cement Ltd
P.O. Rawan, Baloda Bazar
District : Raipur, Chhattisgarh
(2.6 mtpa cement plant commissioned in March 2015)

Energy
Thermal PowerTech Corporation Ltd
TSR Towers,  Block C,
6-3-1090, Raj Bhavan Road,
Somajiguda, Hyderabad 500082
Thermal PowerTech Corporation Ltd
Muthukoor, Krishnapatnam
Andhra Pradesh
(660 MW Unit I of 1320 MW thermal power project commissioned in March 2015)

Electronics
Titan Company Ltd
132/133, Divyashree Techno Park
ITPL Main Road, Bangalore 560037
Titan Company Ltd
Kallapalayam, Coimbatore 641012
(Sub Rs 100 crore state-of-the-art stainless steel watch cases plant commissioned in March 2015)

Work- in - Progress (March 2015)


Real Estate
Ahuja Constructions Ltd
Raj Pipla, Link Road,
Santacruz (West) Mumbai 400054
Ahuja Constructions – Ahuja Tower
Century Bazaar,
Appa Saheb Marathe Marg
Worli, Mumbai 400025
(Rs 300 crore up 53 story premium residential apartments in Central Mumbai under construction)

Engineering -automobile
Isuzu Motors India (P) Ltd
Prestige Centre Court
183, N S K Road, Vadapalani
Chennai 600026
Isuzu Motors India (P) Ltd
Central Expressway
Sri City Industrial Area,
Tada, Andhra Pradesh
(Rs 1,700 crore plant for manufacturing Pick-up trucks being set up)

Civil Aviation
Bengal Aerotropolis Projects Ltd
5, Gorky Terrace,
Elgin,  Kolkata 700001
Kazi Nazrul Islam Airport
Bengal Aerotropolis Projects Ltd
Andal, ^Durgapur, West Bengal
(Rs 650 crore domestic airport under implementation near Durgapur steel city)

Energy
Singareni Collieries Co Ltd
Singareni Building
Kothagudam, Telangana

Singareni Collieries Co Ltd
Pegadapalli, Jaipur Mandali,
District Karimnagar, Telangana
(Work in Progress for 660 MW Unit 1 if 1320 MW thermal power plant in Telangana)