Unit II of Maithon Power Project in Jharkhand commissioned
Tata Power on 24 July 2012 announced
commissioning of its Unit II of 525 Mw of its Maithon mega power project in
Dhanbad, Jharkhand. Maithon Power (MPL), the 74:26 JV between Tata Power and
Damodar Valley Corporation (DVC) has implemented 1050 Mw coal based power
project power in Jharkhand. The project is spread over 1,200 acre.
Unit II of Tata Power’s Mundra UPPP synchronized
Tata Power Ltd has on July 24, 2012
synchronised the 800 Mw Unit II of the 4,000 Mw Mundra UMPP. The Unit I of
Mundra UMPP was commissioned in March 2012. With synchronisation of the Unit
II, the thermal power generation capacity of Tata Power stands at 5,247 MW and
the generation through clean sources such as hydro, wind and solar stands at
852 MW.
L&T commissions new switchgear facility at Vadodara

Larsen & Toubro Ltd : L&T House, Ballard Estate, Mumbai 400001
Radisson Blu Plaza Banjara Hills opens

Carlson Rezidor Hotels India (P) Ltd : DLF Cyber City, Gurgaon 122001
NHPC commissions Chamera III Hydro Power project in Himachal Pradesh
HPC has
commissioned all the three units of its 231 MW (77 MW x 3) Chamera-III hydro
electric project in Himachal Pradesh.
The 231 MW Chamera-III is
a run of river scheme on river Ravi in the upstream of 300 MW Chamera-II
Hydroelectric Project in Chamba district of Himachal Pradesh. The project was
sanctioned by Central Government at a cost of Rs 1,405 crores in 2005.
250 Mw III Unit of Pragati Power Corporation at
Bawana becomes operational
Pragati Power Corporation has commissioned the third 250 Mw advanced-class gas turbine at 1,500 Mw
combined cycle power plant (CCPP) at Bawana in Delhi. This power plant is equipped
with two steam turbines of 250 MW each and can be operated in both open cycle
as well as closed cycle mode. BHEL was entrusted the turn-key contract
of the project.
Pragati Power Corpn Ltd (Govt of NCT of Delhi undertaking), Rajghat,
New Delhi 110002
Mahindra 2 Wheelers R&D Centre opens
in Pune
Mahindra
2 Wheelers Ltd on 4 July 2012 opened its two wheeler Research and Developments
(R&D) centre at Pune. The R&D centre was set up at an investment of Rs
100 crore, will enable Mahindra 2 Wheelers to undertake in-house design and
development of engine technology for its motorcycles.
Sarovar Portico’s new hotel in Bangalore
opens doors
Sarovar
Hotels & Resorts has launched a new property in Bangalore - Davanam Sarovar
Portico Suites. The new hotel has 132
suites ranging from 650 sq ft to 1,200 sq ft with a separate kitchenette along
with comfortable beds, electronic safe and wi-fi connectivity. The newly opened
hotel is the company’s fourth property in Bangalore after Radha Hometel,
Savannah Sarovar Premiere and Park Plaza.
Sarovar Hotels : E - 48/9, Okhla Industrial Area II New Delhi - 110 020
No comments:
Post a Comment